Progress Update : Lany Road Hall Conversion Project

Our Lany Road, Hillsborough House Conversion project continues to progress well on site.

The Insulated SIP Panels have now been installed onto the roof providing the sub structure for the new zinc roof covering.

The Main Contractor Matheson Contracts LLP hope to commence the zinc cladding to the Main Roof in the coming days.

Now that the replacement roof is underway, internal works have re-commenced with first fix joinery and M&E installations  well underway.

The steel supports for the new internal feature staircases have also been installed by sub contractors Macspec Engineering Ltd.

IMG_4029 IMG_3997 IMG_3977 IMG_3966 IMG_3942